The chips still need to fly back to Taiwan to be packaged as packaging partner Amkor's facility in Arizona won't be ready until 2027*. I'm not sure the cause of the delta but it could be in part because Fab 21 got back on schedule rather impressively following earlier delays.
* updated to reflect newer article that Amkor's facility is delayed beyond late-2025
The hardest part is making the chips, no?
Packaging facilities cost ~20% of a fab, right?
Naively, I'm assuming packaging is also not as complicate and difficult as fabrication.
Surely if they can build a fab in the US, they can build packaging facilities, too.